How is a TRIMMING carried out?
This is the adjustment of the line, which must be close to the factory data and the homologation.

Simulation of corrections

The first measurement of the trimming is carried out and interventions are planned to correct it. The tolerance given by the certification (+/- 10 mm) dates from the…

Measurement of the trimming

This involves measuring the ‘total lengths’ of lines, from the base of the risers to the lower surface. This thus takes into account all the manufacturing deviations of…

Trimming adjustment

We intervene in different ways to put things back on track. At the beginning of paragliding, there were 5 to 6 lines per row on each side. We…